| Current |
Stuart & Associates |
President |
UCSD Hillcrest MC Seismic Improvements – Phase II
Seismic upgrade of structural and non-structural components of the Hillcrest Medical Center. The majority of work is located within the Critical Care areas of the hospital, and includes bracing of air handlers, fixed equipment, and piping serving the areas. The project responds to the requirements of SB 1953 for the year 2008/2013. |
IOR - Mark Schrammel
Universtity of California, San Diego |
| Current |
Stuart & Associates |
President |
3874 UCSD Hillcrest O.R. Sterilizers and Equipment Project
A 2900 SF renovation within the O.R. Suite and Sterile Processing Departments, including replacement of sterilizers and washers for surgical instruments.. |
IOR - Eric Dunlavey
Universtity of California, San Diego |
| 2009-2010 |
Stuart & Associates |
President |
3994 UCSD Hillcrest - 64 Slice CT Scanner Installation & Renovation
Renovation of an area of approx. 1654 sq. ft. on first floor of main hospital. A new CT scanner is to be installed. Also included is the remodel of the existing control room, new soiled utility, toilet room, ultrasound room, outpatient holding, IV pump and support spaces. |
IOR - Eric Dunlavey Universtity of California, San Diego |
| 2009-2010 |
Stuart & Associates |
President |
Post Anesthesia Care Unit
The Post Anesthesia Care Unit project is a two-story expansion of the UCSD Medical Center, Hillcrest (200 W. Arbor Drive, San Diego, California) to the east over an approximately 600 SF footprint, including roughly 6,000 SF of site work. Approximately 3,200 SF will be shelled on the first floor for MRI installation and 6,000 GSF renovation of the Post Anesthesia Care Unit (PACU) located on the second floor. |
IOR - Terry Riggs Universtity of California, San Diego |
| 2008-2009 |
Stuart & Associates |
President |
Labor and Delivery Department Renovation
The Labor and Delivery Department Renovation project is an approximate 4,000 GSF renovation and expansion of the Labor and Delivery Department located at the UCSD Medical Center, Hillcrest. The renovation includes five new state-of-the-art birthing rooms, a new waiting room and reception area. |
IOR - Mark Schrammel Universtity of California, San Diego |
| 2008-2009 |
Stuart & Associates |
President |
In-Patient MRI Installation
The In-Patient MRI Installation project is an approximately 3,400 GSF renovation of shelled and occupied space to install a new In-patient MRI Site at UCSD Medical Center, Hillcrest. The MRI suite will feature an extra-large room with a beautiful picture window overlooking Mission Valley and Mission Bay. The facility will be equipped with a Siemens Symphony state-of-the-art MRI scanner. |
IOR - Terry Riggs Universtity of California, San Diego |
| 2008-2009 |
Stuart & Associates |
President |
3776 Hillcrest - Cath Lab Renovation
Replace single plane equipment; modify room as required for new mounting; repair some functional deficiencies (i.e. clean linen; console) & repair damaged millwork. |
IOR - Terry Riggs Universtity of California, San Diego |
| 2008-2009 |
Stuart & Associates |
President |
3993 Thornton CT Scanner |
IOR - Bob Hoffman Universtity of California, San Diego |
| 2008-2009 |
Stuart & Associates |
President |
4130 Thornton MRI Replacement |
IOR - Bob Hoffman Universtity of California, San Diego |
| 2008-2009 |
Stuart & Associates |
President |
4320 Hillcrest OP Cassette Building & Site |
IOR - Terry Riggs
Universtity of California, San Diego |
|
| 2008-2009 |
Stuart & Associates |
President |
3776 Hillcrest - Cath Lab Renovation & Equipment Replacement
Replace single plane equipment; modify room as required for new mounting; repair some functional deficiencies (ie clean linen; console) & repair damaged millwork. |
IOR - Terry Riggs
Universtity of California, San Diego |
|
| 2003-2004 |
Clark Surety |
Project Executive |
Fireman’s Fund Surety for the default J.A. Jones Construction |
IOR – Jonathan Stanley
St. Johns, Santa Monica, CA |
|
| 1999-2000 |
Blake Construction |
Operations Manager |
San Diego State University
Construction of Life Sciences Laboratory |
IOR – Earl Randall
San Diego State University |
| 1995-1998 |
Blake Construction |
Sr. Project Manager |
County of San Diego Inmate Reception Center (Jail)
3rd floor emergency/intensive care unit |
|
| 1990 – 1992 |
CE Wylie Construction |
General Superintendent |
County of San Diego Juvenile Hall
Stand alone emergency room, intensive care unit, primary school |
IOR – Mr. Wylie
|